PROJECT AUTHORIZATION | PACKET ID: N/A |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
67808 | 4 | ||
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
|
NCPD 66-1 (6) |
08-00059 |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
MAJOR WIDENING | 33.0 MI |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
DOH | DOH | DOH | ||
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
DOH/CNTR | DOH |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | FHWA | STATE | DOH | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
8-59.2 | R | 1200 | FD52 | 2004 | 2004 | Q640 | ($3,200,000.00) |
8-59.2 | R | 1100 | FD52 | 2004 | 2004 | Q640 | ($800,000.00) |
8-59.2 | U | 1100 | FD52 | 2004 | 2004 | Q640 | ($1,385,000.00) |
8-59.2 | U | 1200 | FD52 | 2004 | 2004 | Q640 | ($5,540,000.00) |
8-59.2 | C | 1200 | FD52 | 2004 | 2004 | Q050,Q640 | $24,908,225.00 |
8-59.2 | C | 1100 | FD52 | 2004 | 2004 | Q640 | $3,400,000.00 |
CURRENT FUNDING REQUEST TOTAL: $17,383,225.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $0.00 |
DESIGN | $17,931,628.00 |
UTILITIES | $1,350,000.00 |
R/W | $8,000,000.00 |
CONSTRUCTION | $28,308,225.00 |
NON-HIGHWAYS | $0.00 |
Total: $55,589,853.00 |
REMARKS: | THIS MOD. MOVES $4,000,000 FROM R/W AND $6,925,000 FROM UTILITIES TO THE CONSTRUCTION PHASE, PROVIDES AN ADDITIONAL $6,075,000 OF "NCPD" FUNDS AND $11,308,225 OF "NH" FUNDS UTILIZING TOLL CREDITS IN LEIU OF STATE MATCHING. TOTAL ESTIMATE FOR THIS CONSTRUCTION CONTRACT IS $28,308,225. ITEM 8-59.20 |
Project Approval Recommended By: JMY 7/13/2004 |
Signed and Approved by: GS 7/16/2004 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
08-00059.20 | PULASKI
|
8 | SOMERSET NORTHERN BYPASS | KY 461 | 33.0 MI | CONSTRUCT A SECTION OF I-66 FROM THE CUMBERLAND PARKWAY 3MI WEST OF US 27 NORTH AND EAST TO I-75 AT LONDON. |